New challenges had to be met on this special conversion.
|
In brief, the specification was to make a "laboratory"
It had to have 3 phase electrics installed with some 40 double sockets, 6
industrial outlets, lights and control gear.
The main access doors had to remain open in up to 100 MPH winds, a steel
bulkhead with doors had to be installed 3 feet into the standard size 20 foot
long container.
|
An Air conditioning unit along with electrical outlets and Gas bottles had to
all fit within the main doors and the steel bulkhead and all be weather proof.
The internal part of the container was to be lined and insulated whilst the outside
must have no protrusions so as to remain within the ISO regulations for
shipping.
The internal bulkhead was to contain all the specified fitments, that
along with a wide doorway access that used up half the available fixing
space meant that we had to make it all fit like a hand in a glove.
We had the glove..... and made a hand to fit into it perfectly.
|
Top Left
A weather proof enclosure with industrial outlets was fitted to
the steel bulkhead. The Air conditioning heat exchanger was
fitted below and vented to the outside. The pipe work that runs
up to the AC Blower above the doors has been enclosed in a steel
channel to prevent mechanical damage.
Top Right
Gas cylinder mounts were made and installed to hold Gas
cylinders in place, holes through the bulk head to the internal
room for gas lines to pass through.
All the fitments in the first three foot of the container had
to avoid work bench height and the internal fitments to the opposite
side of the walls. |
Air conditioning unit piped up
& ready to feed the internal blower. |
|
Steel Internal Bulkhead door
with security key pad lock, Windows & removable steel shutters. |
|
Above the doors the Internal blower system
is mounted & ducted into main room. |
|
|
The power inlet was made accessible from the outside.
A flush mounted steel enclosure was let into the side of the container.
This was then fully welded into a frame that was welded to the main load
bearing beams to comply with ISO.
A 63amp power inlet was then fitted and a removable door manufactured
to prevent mechanical damage and for shipping purposes.
|
|
The same was done for the exhaust fan of the air
conditioning heat exchange unit.
When finished both the AC and power inlet had removable covers.
The power inlet had to fall just within the main room and the
Exhaust fan had to just fall the other side of the steel bulkhead
and line up exactly with the heat exchanger.
Tolerances were tighter than a tight thing! |
The main internal room was fitted with high grade
fire resistant insulation then fully lined to all walls, ceiling
and internal doors.
The electrical installation then was able to commence. A
distribution board was tailor made to incorporate volt & ampere
meters, switchable from three to single phase & a host of
safety features built in, to meet the customers requirements. This
then also
fed three independent ring mains consisting of 40 double sockets.
Data sockets were also fitted into the trunking.
|
|
|
|
More sockets than you could shake
a stick at!! |
|
The
bulkhead doors being a non standard size and needing to give
high security and remain strong, were made from steel. A keypad
lock, windows with removable shutters, vents to the bottom and
finished internally with insulation and boarded to complement
the high grade finish of the internal room.
Other features to note is the flush Air Conditioning blower
above the doors, Ventilation fan, Gas pipe inlet holes
& Cable duct with flap.
|
Many skills had to be applied and merged
to complete this conversion and we are proud that all the work
was done 'in house' by our team of craftsmen, benefiting the customer with an efficient, cost effective
product.
|
|